Jubilee Vehicle Underframe Modifications Project (JVUM)
Transport for London. Combined from multiple notices.
- Stage
-
Awardthe latest stage the buyer has published
- Buyer
-
Transport for London
- Supplier
-
Engineering Support Group Ltdnamed in the award notice
- Value
-
£9MVAT basis not stated · GBP
- Awarded
-
6 Feb 2024the signed contract date on the notice
- End date
-
8 Aug 2025expected
- First published
-
29 Nov 2022last seen 1 Jul 2024
What the buyer published
The purpose of this procurement is the underframe modification of 96 Tube Stock (96TS)/Jubilee Line rail vehicles. This requirement is subdivided into the following 2 lots. Lot 1) The design, manufacture and supply of underframe modification services. Lot 2) The design, manufacture and modification to the coupler drawgear release mechanism. Economic operators are able to tender for either or both of these lots
In 2019 fractures were found on the longitudinal beams of a 96TS Jubilee Line train's underframe. It was identified through further inspection, that the fractures were not limited to this one train. Those trains that were identified as fit for service (with regards to safety of passengers and LU train operators/ maintainers/ station staff) were returned to service however a large number of trains remained withdrawn until a repair (temporary) was undertaken. The purpose of this procurement is to provide a long-term solution to the fatigue cracking in the vehicle underframe before the short-term repairs are life expired and to resolve associated safety issues with the drawgear load release mechanism. ***Programme and duration of Contract***
Please see the procurement documentation for more details. ***Contract performance conditions***
Successful economic operator(s) awarded a either or both lots will be expected to maintain the following:
- adherence to TfL Health and Safety Policies and Standards,
- adherence to TfL's Privacy and Data Guidelines and GDPR Regulations,
- compliance with Cyber Security Standards,
- compliance with Work Related Road Risk (WRRR),
- compliance with London Living Wage,
- supporting relevant parts of TfL's responsible procurement policy. **How to Apply**
Economic operators must register on SAP Ariba to access the ITT documentation. To register suppliers should follow the link provided directly below. Please search for reference WS1227259766 when you have completed the registration process. https://s1-eu.ariba.com/Sourcing/Main/aw?awh=r&awssk=yKM.p48l&realm=TfL&dard=1
Further guidance and links to useful documentation on registering on SAP ARIBA can be located on the published Contracts Finder Notice ( https://www.contractsfinder.service.gov.uk/Notice/0639b298-6aa1-4091-a48e-f5b99807b964 )
If you have any queries regarding your registration, please email: [email protected]
Additional information can be obtained from the above mentioned tendering portal. The procurement documents are available for unrestricted and full direct access, free of charge once the economic operator completes the registration process in SAP Ariba. Please note that all tender responses must be submitted electronically via SAP Ariba by the ITT deadline stated below
Time limit for receipt of tenders is 1pm (GMT) 27th January 2022
The buyer published this contract more than once.
We combine all notices into one record, so it only appears here once.
| Notice | Published | Type | Stage |
|---|---|---|---|
| 033784-2022 | 29 Nov 2022 | tender | |
| 019890-2024 | 1 Jul 2024 | award |